| Project detail | Information | 
| Project Title: | Design and Build of Buhima-Nalweyo-Bulamagi and Bulamagi-Igayaza-Kakumiro Roads (93km) | 
| Funded by: | Loan funds obtained from China Exim Bank | 
| Engineer: | Kagga &Partners Ltd | 
| Contractor: | M/s. China Wu Yi Co. Ltd | 
| Consultant: | UNRA supervision team | 
| Original Contract Price: | USD. 138,488,356 | 
| Commencement date: | 13th April 2018 | 
| Construction period: | 1099 days (36 months) | 
| Completion date: | 16th April 2021 | 
Project details
The Government of the Republic of Uganda applied for a loan from China Exim Bank and contracted M/s. China Wu Yi Co. Ltd at a sum of USD. 138,488,356 to Design and Build Buhimba-Nalweyo-Bulamagi and Bulamagi-Igayaza-Kakumiro Roads (93km). The works include all field works, detailed engineering and construction of 93km of roads.
Scope of works
The Buhimba-Nalweyo-Bulamagi and Bulamagi-Igayaza-Kakumiro road will be upgraded to Class II (bituminous) standard with a 7-meter wide carriageway and 2.0-meter wide shoulders on both sides of the carriageway. The existing road has an average existing carriage way width of 4.5m with a drain to drain with of 7.5m.
Progress
Cumulative physical progress at end of July is 16.3% against planned cumulative progress of 26%, giving a slippage of 9.7%. Cumulative financial progress at end of July was 27.0% against 34.0% planned. Time progress at the end of July was 474 days (43% of Contract Period). The progress of the Contractor is being tracked based on the revised program of works.