Project details
| Project Details | Information | 
| Project Name: | Upgrading from Gravel to Bituminous Standard of Tirinyi-Pallisa-Kumi Road Project | 
| Funding Agency: | Government of Uganda (GoU) and Islamic Development Bank | 
| Contractor: | The Arab Contractors (Osman Ahmed Osman & Co) | 
| Supervision Consultant: | Construction and Supervision Unit -UNRA | 
| Implementing Agency: | Uganda National Roads Authority | 
| Contract duration: | 36 Months | 
| Contract sum: | 274,124,619,957.01 | 
| Commencement date: | 15th March 2018 | 
| Expected completion date: | 15th March 2021 | 
| Overall physical progress: | 27.00% against 29.35% | 
| Overall time progress: | 534 days (48.79%) | 
| Financial progress: | 33.73% against 34.65% (as extracted from S-Curve August 2019) | 
Project progress
The contractor is undertaking earthworks from CH 19+630-CH 55+500, mostly doing clearing and grubbing, removal of topsoil, roadbed preparation, common excavation swamp improvement, fills, subgrade and sub-base processing. Swamp treatment, gabion and culvert construction at km 41+000-41+980 and km15+100-15+900 is ongoing. Subgrade, subbase and base layer construction is also ongoing from Km 24+780-Km 41+000 with exception of seasonal swamps. The contractor has also started the construction of the Asphalt layer after doing a trial from km35+050 to km 35+100.
 
				